All Systems Operational

Updated a few seconds ago

Lightcrest Status Panel provides insights into maintenances, incidents, outages, and other issues associated with critical Lightcrest infrastructure.

Lightcrest Hosted Operations




Operational

External Services

Scheduled Maintenance

Schedule

July 7, 2016 11:00AM - 11:30AM PDT
July 7, 2016 6:00PM - 6:30PM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

NOTE: This maintenance has been changed to July 7th. Dear Lightcrest Customer, We are augmenting our DNS infrastructure to include additional off-site server locations as a pre-emptive precaution against DOS and other attacks. This will allow for even more robust and reliable DNS services going forward. Our NOC is planning to make this transition Thursday, July 7th, at 11:00:00 AM PDT. There should be no disruption to any services for our customers or Lightcrest internal systems. If you do not have any zones hosted with Lightcrest, no action needs to be taken. If you have zones hosted with Lightcrest, your YPE team will reach out directly to you with further details. Please e-mail support@lightcrest.com if you have any questions. Thank you, Lightcrest NOC
STP MaintenancePlanned Maintenance

Schedule

April 1, 2017 9:00PM - 11:59PM PDT
April 2, 2017 4:00AM - 6:59AM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

Lightcrest will be performing STP maintenance on the network April 1st at 9:00pm PT. This is a low-risk maintenance, however, there is a small probability of a blip during the diagnostics stage.
Shared Netscaler MaintenancePlanned Maintenance

Schedule

May 10, 2017 9:00PM - 9:00PM PDT
May 11, 2017 4:00AM - 4:00AM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

Lightcrest will be performing maintenance on shared Netscaler VPX instances on May 10th at 9:00pm PT. This maintenance will only impact customers who share a VPX instance. The NOC anticipates a small network blip (5-15 minutes) for the impacted VIPs on these instances at this time.
NOC port diagnostics Planned Maintenance

Schedule

June 21, 2017 9:00PM - 1:10PM PDT
June 22, 2017 4:00AM - 8:10PM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

The NOC will be performing port diagnostics on a core switch at 9:00pm PT on Wednesday night. There is considered low risk maintenance.
10G host migrations Planned Maintenance

Schedule

July 26, 2017 9:00PM - 12:00AM PDT
July 27, 2017 4:00AM - 7:00AM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

Select customers will be moved to 10G ethernet switches on 07/19/2017 starting at 9PM PT. These customers will be notified directly.

Schedule

January 30, 2018 8:00PM - 10:00PM PST
January 31, 2018 4:00AM - 6:00AM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

This is an announcement that a maintenance window has been created to address the ROBOT vulnerability in shared NetScaler network device infrastructure. In order to address customer concerns of receiving an 'F' grade on security scans after the SSL Labs cutoff of Feb 1. 2018, we are scheduling this update for tomorrow night at 2018-01-30 20:00:00 PST - 2018-01-30 22:00:00 PST Although there are 2 hours allocated for the maintenance window, we expect there to only be a brief disturbance of several seconds to 5 minutes. If you are on shared NetScaler infrastructure (meaning you do not have a dedicated NetScaler instance), you can expect a very brief outage. Dedicated NetScaler customers have been notified directly of either a corresponding window, or will be notified of a separate maintenance window going forward. Thanks, and as always if you have any questions please email support@lightcrest.com
Dashboard MaintenancePlanned Maintenance

Schedule

February 15, 2018 9:00PM - 9:30PM PST
February 16, 2018 5:00AM - 5:30AM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

Lightcrest will be applying security-related patches to one of its internal servers that provides Kahu dashboard functionality . Only customers who utilize Kahu dashboard functionality will be affected by this maintenance the duration of which is expected to be 30 minutes maximum.

Schedule

August 17, 2018 9:00PM - 10:00PM PDT
August 18, 2018 4:00AM - 5:00AM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

The maintenance planned for 9:00 p.m. PDT this evening is canceled. (Shared firewall reboot.)

Schedule

August 17, 2018 9:00PM - 10:00PM PDT
August 18, 2018 4:00AM - 5:00AM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

The maintenance planned for 9:00 p.m. PDT. this evening is canceled.

Schedule

August 27, 2018 10:10PM - 11:00PM PDT
August 28, 2018 5:10AM - 6:00AM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

This maintenance is complete.
Postponed MaintenancePlanned Maintenance

Schedule

May 27, 2020 1:00AM - 7:00AM PDT
May 27, 2020 8:00AM - 2:00PM UTC

Components

Lightcrest Hosted Operations

Locations

Primary Data Center

Description

Nondisruptive network maintenance previously scheduled for tonight (5/25/20) at 11:00 pm PDT is postponed until 1:00 am PDT on 5/27/20.